CORPORATE EXPERIENCE IN MULTI-DISCIPLINE OIL & GAS PIPELINE PROJECTS.

 

 

 Delcon has been in the business of managing Swamp Pipeline Construction for 16 years for SPDC and CHEVRON. Our specialty is Swamp Pipeline and Flowline Construction and maintenance.  

 

 

RECENTLY COMPLETED PROJECT

Delcon recently completed the construction of the Onshore portions of Offshore flowlines 16in Associated Gas and 24in Export Gas Pipelines all for Forcados Yokri Integrated Project.  (FYIP) 

 

 The scope covered the construction of :

 

·         25 x 500m of 6” Flowlines

 

·         3 x 500m of 8” Flowlines

 

·         1.1km of 24” AG Concrete Coated Pipeline

 

·         7.5km of 16” AG Concrete Coated Pipeline

 

·         8.3 km of 24” EG Concrete Coated Pipeline

 

The work  consumed 520,000 man-hours and involved 140 people all working at the same time.

 

 
 

                

 

 
   

 

 

 
  Click here to view some pictures and schematic layouts of Pipelines / Flowlines constructed by DELCON    
         
 

10 YEARS CORPORATE WORK EXPERIENCE

 

·           1997/1999 swamp flowline Campaign in Odidi Egwa 1 and 2 fields involving replacing and constructing new 4’’ and 6’’ flowlines and gas lines.

 

 

·           1999/2001 Swamp Flowline Campaign (¦ $ 7.0 million) in Yokri, Egwa, Otumara involving replacement of 4’’ and 6’’ lines as well as 9 Bulk Production Manifolds.

 

 

·           2002/2003 Swamp flowline replacement for CHEVRON  (¦$1.2 million)

Involving replacement of 4’’, 6’’ and 8’’ Swamp flowlines at Robertkiri (in joint venture with Benek Engineering of P/H ).                       

 

 

·           November 2003/April 2004 Construction of 22.4Km of 6in and 8in Swamp flowlines ($ 3.4 m + N107.26m) at Yokri on Forcados Yokri Integrated Projects.

 

·           2004/2006 - 7.6 km 16” AG and 8.4km 24” EG Concrete Coated Pipe Lines ($9.8m +  N307.9m) for SPDC on FYIP.

 

 

 
 

             

 

 
 

 

MORE PROJECTS EXECUTED

 

 

 
 

S/N

WORK DESCRIPTION

CONTRACT NO

VALUE

CLIENT

PERIOD 

1

Swamp Flowline Construction and maintenance

W0170 Callout

 

N123.2 million

 

SHELL- Warri

June 1991–December 1993

2

Swamp Well head Upgrade

E-0266

 

N29.4 million

 

SHELL – PH

June 1993–December 1994

3

Swamp Flowline Construction and maintenance on Sapele West, Odidi and Egwa

W00427 Callout

N16.1 million +

$1.6million

 

 SHELL- Warri

June 1996–December 1998

4

Swamp Flowline Construction and Maintenance)

W07257

N167.8 million + $5.6 million

  

SHELL - Warri

Jan 1999–October 2001

5

Swamp Flowline Construction

FAC-2002-10030430 J.V with Benek Engr. Port-Harcourt

$737,478.90

72% of Total final value of RBK works including Service Orders in Dollars

Chevron Texaco

October 2002 To June 2003

6

Swamp Flowlines for Forcados Yokri Integrated Project FYIP

SUB-CONTRACTNO: SECL/W06382/Comm-Subcon/018

$3.4 million + N107.26 million

  

SHELL - Warri

October 2003 To June 2004

7

16”/24” AG/EG Pipelines on FYIP

SUB-CONTRACTNO: SECL/W06382/Comm-Subcon/018

$9.8 million + N307.9 million

SHELL - Warri

October 2004 To March 2006

8

24” AG Pipelines and 4 x 8”

Gas Oil Lines on FYIP

SUB-CONTRACTNO: with Willbros

$.74 million + N31.1 million

Willbros/SHELL

March 2006  To May 2006

 

 

 
 

           

 

 
   

 

 

 
 

Our work experience also includes the following:

 

1.       >   onstruction of 2 x 6 Well Cluster Platforms for DI / SHELL

 

2.       >   78 km Land flowlines at Shell Ogini Field

 

3.       >   Installation of BCF Tank Fire Fighting facility at Shell Forcados Terminal.

 

4.       >   Flare Line and Stack replacement at Odidi, Egwa I and Egwa II Flowstation

 

5.       >   Complete Flowstation Refurbishing at Batan for Shell (Warri)

 

6.       >   Pump House (3 Pump bay) construction at UQCC

 

7.       >   Trunk Line pigging manifold upgrade at Forcados North bank.

 

 
 

      

 

 

 
 

 

 

 

 

 

Construction Challenges              

We faced two major challenges in the execution of FYIP works

I.                                                             Construction of 16” and 24” Concrete Coated pipelines in a Land Locked Swamp ROW with zero access for a Lay Barge posed the first challenge. 

                                                            We dismantled the Lay Barges and assembled all Construction hardware in 6 x 40’ containers.  These were assembled by Swamp Cranes on a sand filled island.  The Lines are now completed.

  

ii.                                                                                                                                                                                                                                                                                        The second challenge is from the by-pass.  The Two Gas pipelines are routed to by-pass Sokebolou Community crossing two small Creeks that provide the only access to the Community.  The terrain is entirely Mangrove Swamp and the Creeks are too small for a Lay Barge.  Once again the containerized Lay Ramp were deployed and the entire 1.03km section fabricated.  Floating and Sinking was done in one day and thus avoid obstructing the Community in any way. To ensure free stress profiles for the creek crossings dredging of 450m channel 9m wide x 6m deep was undertaken with our Grab Dredger.

 

 

 

 

 

 

 

TOP

 

DISCLAIMER


Delcon Engineering Company Limited

End of Sedco Road - P.O. Box 401, Effurun - Delta State - Nigeria

Tel: (234) 08039312754. E-mail: delconltd@gmail.com